Toronto Building Permit Status: How to Check and What It Means
Toronto building permit status explained: how to search it, what each status in the City's glossary means, review timelines and what to do at each step.
To check Toronto building permit status, search your address or permit number on the City of Toronto's permit status tool, then match the status shown to the City's glossary. The tool is updated as of the previous business day, so a change you made today will not appear until tomorrow.
This guide explains what each status means, what you can do at each one and when to ask for help. If you are still deciding whether your project needs one, start with our permit and zoning page and the Toronto building permit checker.
The City's permit status page covers active permits that are 10 years old or less from the application date, and permits closed or cancelled for no longer than one month. An older closed permit will not appear there.
How do you check a Toronto building permit status?
Open the City's status search, enter the property or permit details it asks for, and read the status shown. The City says the data is updated as of the previous business day, and it points questions to 311.
Have these ready before you search:
- The permit or application number from your intake email, if you have it.
- The property address exactly as the City records it.
- The access code from intake, which you also need to upload drawings to the File Submission Hub.
What does each permit status mean?
The statuses below are the ones most homeowners meet, using the definitions in the City's glossary. Read the right column as a prompt for your next move, not as legal advice.
| Status | What the City says it means | Your next move |
|---|---|---|
| Application Received | Arrived, but not yet accepted or processed | Confirm the application is complete |
| Application Acceptable | Submission requirements met, intake pending the initial permit fee | Pay the initial fee so intake can finish |
| Not Started | Accepted, but review has not begun | Wait; check the review stream timeline |
| Under Review | Review has started but is not finished | Wait; keep your designer reachable |
| Notice Sent / Examiner's Notice | Deficiencies found; the examiner awaits your response | Answer every item through the File Submission Hub |
| Response Received / Accepted | Your response was submitted and the file is back in the review queue | Wait for the next result |
| On Hold | On hold because of missing information | Supply what is missing |
| Refusal Notice | Review resulted in a refusal | Address all listed items before responding |
| Issuance Pending | Review complete, other approvals or fees outstanding | Find what is outstanding |
| Ready for Issuance | Review complete; can be issued at any time | Ask whether related permits must issue together |
| Permit Issued | The permit has been issued | Book inspections as work progresses |
| Inspection | Issued and under active inspection | Request the next inspection when work is ready |
| Violation | An inspection order is attached to the permit | Read the order and correct it |
| Cancellation Pending | Dormant over five months; notice sent by registered mail | Respond within a month |
| Permit Revoked | The permit has been revoked | Ask Toronto Building about a new permit |
How long should each stage take?
The City of Toronto publishes target review times in business days for complete applications on its building permit review streams page. They are targets, and the page gives no timeframe for incomplete applications.
| Stream | Covers | Target |
|---|---|---|
| House Stream | Houses with no more than two dwelling units, plus garden and laneway suites | 10 business days |
| Small Building Stream | Part 9 buildings that are not houses | 15 business days |
| Large and Complex Building Stream | Part 3 buildings | 20 business days (large), 30 (complex) |
| Express Services | Certain small residential, commercial, solar and sign projects | Within 3 business days of intake, as a goal |
Applications without an issued Zoning Applicable Law Certificate are treated as incomplete. To estimate a window for your own project, try our Toronto permit review time calculator.
What should you do when a Notice Sent status appears?
Answer every item, in one drawing submission. The City's plan review process says to combine drawings into a single PDF, add revision bubbles and submit only revised pages. Only one drawing submission is accepted at a time, and no more uploads are allowed until the assigned examiner accepts it.
Supporting documents go by email to the assigned examiner, with the application number and address in the subject line. The page gives no response deadline, so ask your examiner how long you have. The same page says that a zoning problem can be taken to the Committee of Adjustment; our minor variance guide explains that route.
What does the City check while a permit is under review?
The City's plan review process page lists the checks in order. A Zoning Examiner checks the zoning by-law: land use, building size and density, placement, lot sizes, parking and height. A Building Code Examiner then checks the Ontario Building Code for health and safety, fire protection, structural sufficiency, materials, plumbing and mechanical systems.
Plans are also checked against heating, plumbing, drainage and private sewage requirements where they apply, and certain multi-family, commercial, industrial and institutional applications with fire protection systems get a Fire Code review. A notice is the City's written record of why the project does not comply, so each item on it maps to one of these checks.
A common mistake is replying to a notice with a verbal fix or a loose sketch. The City accepts revised drawings only through its File Submission Hub, and a reply that never reaches the examiner leaves the status stuck at Notice Sent. Ask your designer to tick off each notice item against the revised page that answers it before you upload.
Why does a permit stay open after the work is finished?
A permit does not close itself. The City's closing building permits page says a permit stays open until every inspection is complete and Toronto Building formally closes it, and that no inspection for 18 months makes it dormant.
The same page says an open permit can delay a sale or financing, and a permit older than 18 months with no inspections requested can receive a Notice of Intention to Revoke. That is not a revocation yet: you must request an inspection before the deadline in the letter and show that work has genuinely started.
The City's inspection pages say you can request an inspection online, and they ask for the permit number and the contact details of the person who will be on site. A voicemail request is not scheduled until an agent calls back.
What if you bought a house with an old permit?
You are responsible for it as the current owner. The City says to confirm what work was done, then request a final inspection, apply to transfer the permit to continue the work, or ask for an inspection so Toronto Building can decide the next step. Ask your lawyer to search for open permits before a purchase closes.
What should you have ready before you call us?
- Your permit number and the status you see today.
- Any notice or letter you received, with its date.
- The drawings you submitted and who prepared them.
- The type of project, so we can tell which review stream applies.
- Whether work has started, and whether any inspection has been done.
If you plan a project that will need a permit, such as a home addition or basement underpinning, our guide to renovation permits in the GTA shows what to settle first. When you are ready for a written quote, contact us with your plans and photos, and we will tell you what we need to see before we price it. Our permit and zoning page explains how we plan around approvals.
Frequently asked questions
What does Application Received mean on a Toronto building permit?
It means the application has arrived at Toronto Building but has not yet been accepted or processed. Nothing is wrong at this point; the review clock described by the City's review streams applies to complete applications, so check that the application is complete.
What does Ready for Issuance mean?
The City's glossary says review is complete and the permit can be issued at any time. Related mechanical or plumbing permits may need to be issued together, so a permit can wait in this status while the others catch up.
Why does the status show Notice Sent or Refusal Notice?
Notice Sent means review has begun, deficiencies were found and the examiner is waiting for your response. Refusal Notice means review ended in a refusal, and the City advises addressing every listed item before you respond to the examiner.
How often does the City update the permit status?
The City's status page says the information is updated as of the previous business day. A change you made today, such as a resubmission, will not show until the next business day.
How long is a permit open, and what happens if I never close it?
A permit stays open until all inspections are done and the City formally closes it. The City treats a permit with no inspection for 18 months as dormant, and can issue a Notice of Intention to Revoke, so schedule the final inspection when the work is finished.
Book a consultation for your project
Tell us about the space, the scope, and your timeline. Our design team reviews it and replies with the next step.